Project Details

Project
Harbour Town Car Park Redevelopment
Client
ADCO Construction
Location
Harbour Town
Contract
$1.7m
Period
8 months
Year Completed
2016

Project Overview

Universal Civil Contracting was awarded the contract works for this 16,000m2 carpark in October 2015, with a very strict programme to have the carpark completed and handed over in time for the Christmas Shopping rush. Universal Civil completed the carpark in 8 weeks. After the car park was handed over on time and on budget, Universal moved to the civil works on the Extension to building 3B.
Have you got a project you would like to discuss?

Tell us more about your project and a member of our team will contact you directly.

    More Articles
    • 25 August
      Farewell to a True Workhorse – “By Crikey”
    • 18 January
      Project Kick Start – TAFE Coomera Marine Centre
    • 5 August
      Official Opening of Chermside Hockey
    • Rewarding letter of commendation for our client
    • 20 March
      Hard Day in the Office for The Boys
    • Proud Sponsors of Young Care in Support of Teneille Vassie
    Building Queensland’s future with innovative and reliable infrastructure solutions.