Project Overview
Client:FKG
Location: PIMPAMA QLD 4209
Contract: $3.8MIL
Period:MAR 2020 – JAN 2021
Scope of Works
Universal Civil was first awarded the early works package in March.
This package involved the removal all existing vegetation over a 57000m² block, topsoil screening and tree mulching. Following this, Universal Civil was then awarded the full civil package.
CONTRACT WORKS
- Bulk Earthworks
- Detailed Excavation
- Stormwater
- Sub Soil Drainage
- Pavements
- Concrete Footpaths and Driveways
- Asphalt
- Line Marking and Signs
All works were completed for the client in a timely and professional manner; maintaining a strong and respectful relationship.